Campaign Project Update
Church Restrooms

The Capital Campaign Building Committee has been working diligently to accomplish project tasks.   Hadley Specialty Contractors refurbished the exterior of six windows and the interior of three windows in the sacristy over the past several weeks.  Repairing these six windows has given us a much better  idea of the general extent of the damage to the windows, how the windows are constructed, and the cost required to repair them.  After a report summarizing Hadley’s findings, Thompson Engineering will finalize specifications for bid purposes for the remaining windows.

Church Restroom renovations have begun in June and should be completed by August.  This project designed by Cummings Architecture with work to be done by Stirling Contractors.

Click the image below for the full sketch.